Luriware Consulting Agricultural Engineers
Changing the face of structures in Agriculture

Mpumalanga Province

Luriware (PTY) LTD  has a wide range of skill and experience of it's Members hence the firm is working on a number of Projects. Tabled below are the Projects the firm is currently working on in the Mpumalanga Province. 

                                                     

Project

Project Description

Project Progress


GERT SIBANDE DM

Siyapambili Poultry House

  

Siyaphambili: It’s a Fortune 40 project which is a development of a 2 x 25000 conventional broiler houses and other supporting infrastructures in Mkhondo local municipality, Gert Sibande district, Mpumalanga province. 




COMPONENT OF WORKS DONE:
- Brick work and concrete works 90%     done

- Steel works 100% done ( structure            plus roof)

- Assembling roof trusses  


COMPONENT OF WORKS REMAINING:
- Plumbing
- Mechanical and Electrical Equipment    fittings

- Aesthetic works (tiling, plastering        and painting)

- Testing and practical completion

Project Overall: 75% done

GERT SIBANDE DM

Perdekop Poultry Housing 

  

PERDEKOP: It’s a fortune 40 project, which is a development of 2 x 25000 poultry house in addition of existing infrastructure. It also involves construction and installation of a park homes village. The site is in Gert Sibande District, Pixley Ka Seme local municipality.



COMPONENT OF WORKS DONE:
- Site establishment
- Staking out
- Site clearance

COMPONENT OF WORKS REMAINING:

- Construction of the houses (from           concrete works, steel works,                    Equipment, electrical, and aesthetic  works)

- Platform creations for construction      of the houses

- Testing and practical completion

Project Overall: 10% done

EHLANZENI DM

Nkomazi 500 cattle feedlot

  

NKOMAZI FEEDLOT, MZINTI: This project is in Ehlanzeni South District in Nkomazi Local Municipality. Luriware (PTY) LTD was appointed to plan, design, implement and supervise on the construction of 500 cattle feedlot and supporting infrastructures which are an administration block, storage shed, ablutions, drilling of borehole and fencing of the feedlot area.

In the meantime, the site has been handed over to the department, but since the contractor have not finished some petty stuff, they have been given time to finish then the final site handover will be done. 


COMPONENT OF WORK DONE:

- Site Clearance

- Earthwork for slope creation for feedlot and hospital pens

- Construction and formation of entrance and internal roads

- Culvert waterway and drainage pipes -Diversion banks and drainage canal construction                                         

- Construction of silage banners

- Construction of manure lagoon and sedimentation zone

-  Constructing the feedlot

- Perimeter and Security fencing

- Establishing the storage shed

- Constructing the administration block

- Constructing a machinery shed 

COMPONENTS OF WORK REMAINING 

- Lining the dam 

- Testing and practical completion


Project Overall: 95% done

EHLANZENI   DM 

Mawewe Earth Dam

Mawewe Earth Dam, it’s rehabilitation of an existing dam, in Nkomazi Local Municipality in Ehlanzeni South, Mpumalanga.

On Friday 25 November 2016 the contractor was appointed. 

The Site Handover meeting was held on 29 November 2016 at Nkomazi Local Municipality Home Affairs.

The site has since been handed to the contractor who is now busy on site.

COMPONENTS OF WORK DONE:

  • The contractor has just been appointed hence no work has been done


COMPONENTS OF WORK REMAINING:

- Site Clearance 

- Dam preparation

- Excavate and spoil saturated material from stream center-line and core

- Excavate, place and compact suitable material to dam walls including shaping, stocking, drying etc

- Boulder Excavation. Stockpile for use as rip rap(if instructed by engineer)

- Ripping intermediate material in spill way excavation 

- Excavate and place toe drain along toe to main embankment

- Trench and back-fill trickle flow pipe  

- Supply, test and commission bed and lay complete with bell and spigot joints and rubber seals

- Construct Trickle flow box

- Reinforcement for spillway concrete sills

- Core foundation preparation by cleaning exposed rocks by hand removal of loose material

EHLANZENI DM 

Allandale Citrus Farm in

BUSHBUCKRIDGE LM

  

Allandale Farm, 10 ha drip irrigation system. At the moment this farm is not operating or generating any income due to poor and vandalised infrastructures, since this farm was abandoned for a long period of time.The works are to resuscitate the farm and bring it back to its full potential.

The works are to rehabilitate and replacing some of the existing infrastructure such as road networks, electrification, building of new administration houses, plumbing and storage. 

The contractor hasn't been appointed, the project is still on advertisement phase.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          

COMPONENTS OF WORK TO BE DONE:

- Site Clearance 

- Setting up road networks 

- Setting up offices and storage facilities

- Setting up toilets and ablution facilities

- Provision of water, power and communication facilities

- Supply and installation of KSB Etanorm 

- Supply and install pump station accessories

- Supply, install, terminate and commission 6 square millimeters SWA core copper cable from transformer to electric panel 

- Supply, install and commission 18.5 kW 2 pole 400 V electric motor

- Supply, install and commission 18.5 kW Electrical soft starter switch gear

- Supply, install and commission 40kVA 3 Phase 400V diesel powered generator set 

- Supply electrical transformer 11kV/400V 50kVA

- Test and issue CoC of the complete electric installer of the irrigation system 

EHLANZENI DM

Magogeni Auction Facility

  

Magogeni Auction Facility. It is still on Environmental Impact Assessment phase. 



NKANGALA DM

Letolo Renovations for 2 existing Poultry Houses in 

SYDBRANDSKRAAL

  

Letolo Phase 2 Poultry Project: Renovations of 2 x 40 000 environmentally controlled houses.

- Testing was done on 24 October 2016, the houses were functioning but there were a few snags on the houses, the houses will be worked on further and the houses would have been re-tested by Friday 9 December 2016.

COMPONENT OF WORKS DONE:
- Components of the                    structure(doors,walls) have been  repaired and some replaced

- Electrical and instrumentation are  90% done

- Electric perimeter fence has been           completed

- Mechanical equipment 80% done

- Installations of computer systems      (electrical and instrumentation)

- Fitting of wet wall pumps and fan    motor (Mechanical systems)

COMPONENT OF WORKS REMAINING:

- Testing and practical completion


Project Overall: 95% done

Nkangala DM

KWAGGAFONTEIN MYFIP 

FORTUNE 40

THEMBISILE HANI LM

Kwaggafontein Fortune 40, Installation of four tunnels for young farmers programme to be guided on how to grow vegetables and to be motivated in farming so that they can survive through farming. Other works involve installation of park homes consisting of two classrooms for incubators, two ablutions facilities, kitchen, office and the switchboard room. And also drilling, equipping and reticulation of four boreholes that will supply water to the tunnels and park homes. Installation of solar panel and a standby generator to supply power to the water pumps and the rooms. And also fencing of tunnels and park homes area. Construction of road networks, machinery shed and fencing of the whole area.

Kwaggafontein Project is going very well. All other works mentioned above have been completed, now we are waiting for the construction of machinery shed and road networks. 

In the mean time production is taking place on the tunnels. The contractor hasn't been appointed for the components of work remaining hence the progress is at a stand still in the mean time.

- A contractor was appointed for the drilling of two boreholes

- A contractor was appointed for fencing the whole site 

The site will soon be handed to the contractors 

COMPONENTS OF WORK DONE: 

- Site Clearance

- Supply and installation of tunnels

- Water storage tank fitting 

- Installation of park homes

- Drilling, equipping and reticulation 4 boreholes 

- Installation of 8 solar panels 

- Supply, install and commission 40kVA 3 Phase 400 V Diesel Power Generator

- Fencing the tunnel and the park homes


COMPONENTS OF WORK REMAINING:

- Drilling and equipping two boreholes 

- Construction of the machinery shed

- Setting up of road networks 

- Construction of a Health and Safety Plant 

- Construction of an administration block 






Project Overall: 70% done

Nkangala DM

DELMAS ENVIRONMENTAL CENTRE

THEMBISILE HANI LM


DELMAS site assessment, scoping and BOQs completed. Now waiting for the contractor to be appointed for renovations of the existing structures at Delmas Environmental Center.

- The site has been handed to the contractor 






COMPONENTS OF WORK TO BE DONE: 

- Renovation of the administration block 

- Renovation of Hall and stage

- Renovation of grey hall 

- Renovation of assembly point

- Renovation of staff room

- Renovation of client staff room

- Supply and Installation of picnic tables 

Ehlanzeni South DM

BOSCHFONTEIN MYFIP

FORTUNE 40

Boschfontein Fortune 40 it is situated in Ehlanzeni South District, the work involves the supply and supervising the installation of the park-home containers.

On 21/10/2016 containers were delivered on site, these containers include: 

1. 6m x 2.4m container - Storage Unit

2. 12m x 2.4m container - Male and Female ablution split

3. 12m x 2.4m container - Male and Female accommodation split

4. 6m x 2.4m Kitchen - Office 

5. 6m x 2.4m container - Classroom Unit 

Luriware (PTY) LTD was appointed for the installation of the park homes, the contractor has been appointed and the site handover meeting will be done soon

COMPONENTS OF WORK DONE:

Delivering containers which include:

- 6m x  2.4m container - Storage Unit

- 12m x  2.4m container -  Male and Female ablution split

- 12m x  2.4m container - Male and Female accommodation split

- 6m x  2.4m - Kitchen office

- 6m x  2.4m container - Classroom Unit  

COMPONENTS OF WORK REMAINING: 

- Supervising the installation of the park homes 




Project Overall: